Anticipated work for next week for the 2019 Street and Utility Improvements Project includes:
Elm Drive: restoration grading is scheduled to occur towards the end of next week, weather permitting.
Diedrich Drive & Kirche Hill Drive: restoration grading is anticipated to occur towards the end of next week, weather permitting.
Sunny Ridge Drive & Lylewood Parkway: street excavation is scheduled to continue throughout next week.
For more details about the project or to sign up for project updates, please visit the project page at: 2019 Street Improvement Project.